Timeline

Gantt & review delays

Buddy work in sage, client reviews in cream. Enter actual review days below — the schedule shifts automatically.

Gantt timeline
21 May15 Sept
+6 days from Buddy build time
+26 days added by client reviews
21 May
28 May
4 June
11 June
18 June
25 June
2 July
9 July
16 July
23 July
30 July
6 Aug
13 Aug
20 Aug
27 Aug
3 Sept
10 Sept
1. Kickoff & Discovery
3d
2. Tailor & Align Content
5d
3. Screen Design
7d(+2)
review
4. Storyboard
14d(+4)
review
5. Alpha Build (Storyline)
10d
review
6. Narration & Polish (Beta)
4d
7. QA & Gold Delivery
4d
review
Buddy work Client review Delayed review

Buddy build time

Enter the actual days Buddy took to build each phase. Anything over the planned days pushes the schedule forward, just like a late review.

Kickoff & Discovery
Phase 1
Planned
3 days
Delay impact
On time
Tailor & Align Content
Phase 2
Planned
5 days
Delay impact
On time
Screen Design
Phase 3
Planned
5 days
Delay impact
+2 days
Storyboard
Phase 4
Planned
10 days
Delay impact
+4 days
Alpha Build (Storyline)
Phase 5
Planned
10 days
Delay impact
On time
Narration & Polish (Beta)
Phase 6
Planned
4 days
Delay impact
On time
QA & Gold Delivery
Phase 7
Planned
4 days
Delay impact
On time

Client review time

Enter the actual days each review took. The Gantt updates automatically — extra days push the schedule forward.

Design / Structure approval
Phase 3
Planned
2 days
Delay impact
On time
Storyboard approval
Phase 4
Planned
3 days
Delay impact
+26 days
Alpha approval
Phase 5
Planned
3 days
Delay impact
On time
Gold / Final approval
Phase 7
Planned
2 days
Delay impact
On time