Timeline

Gantt & review delays

Review delays and received feedback are shown in red. Remaining work reflects recorded Buddy delivery speed, with client review time kept separate.

Project timeline snapshot

21 May 2026 → 21 Dec 2026 · pace-based final estimate

+69 business days · client reviews+6 days · recorded Buddy delay16 days · Buddy revisions
Phase & dates
21 May18 June16 July13 Aug10 Sept8 Oct5 Nov3 Dec
✓ 1. Kickoff & Discovery
21 May → 26 May
Build: 3d · planned 3d
✓ 2. Tailor & Align Content
26 May → 2 June
Build: 5d · planned 5d
✓ 3. Screen Design
2 June → 15 June
Build: 7d · planned 5d
4. Storyboard
15 June → 6 Nov
Build: 14d · planned 10d
Review delay +69 business days
Feedback received · 15 Oct · +69d delay
5. Alpha Build (Storyline)
6 Nov → 1 Dec
Forecast build: 14d · planned 10d
6. Narration & Polish (Beta)
1 Dec → 9 Dec
Forecast build: 6d · planned 4d
7. QA & Gold Delivery
9 Dec → 21 Dec
Forecast build: 6d · planned 4d
Buddy build Delayed review / feedback received Planned client review Buddy revisions Snapshot · 4 Nov

Forecast build durations use 1.40× planned time from recorded Buddy work (screen design 7/5 days; storyboard 14/10 days). Client feedback received 15 October, not sign-off. Script/Storyboard v2 was delivered 4 November, ahead of the 6 November target; future reviews assume planned allowances and immediate approval. Weekends excluded; holidays, shutdowns and further delays are not included. Earlier phase dates are schedule-derived; the storyboard review start is confirmed as 7 July.

Buddy build time

Revision window: 15 October → 4 November · 14 business days. Script/Storyboard v2 and updated images were delivered 4 November, ahead of the 6 November target. Designer leave and consolidating feedback contributed to turnaround.

Enter the actual days Buddy took to build each phase. Anything over the planned days pushes the schedule forward, just like a late review.

Kickoff & Discovery
Phase 1
Planned
3 days
Delay impact
On time
Tailor & Align Content
Phase 2
Planned
5 days
Delay impact
On time
Screen Design
Phase 3
Planned
5 days
Delay impact
+2 days
Storyboard
Phase 4
Planned
10 days
Delay impact
+4 days
Alpha Build (Storyline)
Phase 5
Planned
10 days
Delay impact
On time
Narration & Polish (Beta)
Phase 6
Planned
4 days
Delay impact
On time
QA & Gold Delivery
Phase 7
Planned
4 days
Delay impact
On time

Client review time

Storyboard feedback received 15 October. The recorded client review stops there; revisions after that date are Buddy time, not additional client delay. Business days exclude weekends, not public holidays.

Enter the actual days each review took. The Gantt updates automatically — extra days push the schedule forward.

Design / Structure approval
Phase 3
Planned
2 days
Delay impact
On time
Storyboard approval
Phase 4
Planned
3 days
Delay impact
+69 days
Alpha approval
Phase 5
Planned
3 days
Delay impact
On time
Gold / Final approval
Phase 7
Planned
2 days
Delay impact
On time