Reviews & sign-offs
Approval gates
Buddy only moves to the next phase once the current one is approved.
Reviews left longer than planned automatically push the schedule. See the Gantt for the live timeline.
Review · Phase 3
Design / Structure approval
Reviewer · Vinnies team
Planned
2 days
Review · Phase 4
Storyboard approval
Reviewer · Vinnies team
v1 sent 7 July 2026 · feedback received 15 October 2026 (72 business days, +69 against the 3-day allowance). Script/Storyboard v2 delivered 4 November 2026 — awaiting consolidated review and sign-off.
Script/Storyboard v2 sent 4 Nov · Awaiting consolidated review · Approval pending
Planned
3 days
Review · Phase 5
Alpha approval
Reviewer · Vinnies team
Planned
3 days
Review · Phase 7
Gold / Final approval
Reviewer · Vinnies team
Planned
2 days